From a signed lease to an energized data center
TeraWulf’s agreements with Fluidstack grew to 380 MW. The path from signing to operating capacity differed building by building.
How the study works
The initial August 2025 lease covered more than 200 MW of critical IT load. A second agreement added 160 MW. Subsequent disclosures reported 380 MW contracted. The study keeps each event’s date, scope and unit.
What the evidence shows
Lake Mariner reported 81 MW of revenue-generating capacity at the end of June 2026 and 102 MW in July. Meanwhile, the stated CB5 target moved from energization in Q4 2026 to phased delivery beginning in early 2027.
Limits of the evidence
The operating figures describe the whole campus; the contracted figures describe Fluidstack. Subtracting one from the other would invent a customer backlog. Neither reports actual GPU utilization.
Primary sources