The financing came before the GPUs

The Microsoft–IREN–Dell chain shows how a cloud agreement becomes a hardware commitment before a customer takes delivery.

How the study works

IREN announced a five-year, $9.7 billion cloud contract with Microsoft in November 2025, with a 20% prepayment. It also placed approximately $5.8 billion in equipment orders with Dell.

What the evidence shows

In February 2026 IREN said $3.6 billion of GPU financing and a $1.9 billion prepayment covered about 95% of GPU capital expenditure. A March purchase agreement for over 50,000 B300 GPUs limited rescheduling and made orders non-cancelable and non-returnable.

Limits of the evidence

Installation had begun by the May update. That report still described a Q3 handover as a target. The financing, purchase commitment, installation and customer acceptance are separate milestones.